Willerby Phase 2

RETURN VISIT TO ONGOING HOUSE DEVELOPMENT IN YORKSHIRE 

A king post wall completed for a residential site in Willerby.

Project Description

SCOPE OF WORKS c. 70 linear metres of king post wall up to 3m retained height
CLIENT Beal Homes
EQUIPMENT ABI TM14/17 leader rig
CONSTRUCTION PERIOD 7 days on site

Aarsleff returned to this site in Willerby to deliver a second phase of King Post Wall installation. The site was live with lots of third party activity. Careful logistical organisation was needed to work with Beal Homes and the groundworks contractor to complete the project safely, beating the target programme. 

The site manager, Phillip Evenden of Beal Homes said, “Great performance from Aarsleff on site, good bunch of lads to work with.”

Our Graduate Engineer, Alex Boyle, said, “A positive return visit for AGE to this site in Willerby, Beal Homes were complimentary of our professionalism and look forward to having us back on site to complete the 3rd and final visit.”

Aarsleff will return to the site in 2023 to complete the final phase of king post wall.