Offshore Windfarm

INSTALLING CFA PILES FOR A GAS MAIN BRIDGE.

A wide angle shot of a Soilmec SF50 piling rig in use at the Triton Knoll Offshore Windfarm project.

Project Description

SCOPE OF WORKS 8no. 600mm diameter piles, 15m lengths
EQUIPMENT Soilmec SF50
CLIENT Triton Knoll
CONTRACTOR Siemens
CONSTRUCTION PERIOD 12th August – 20th August 2019

Aarsleff Ground Engineering has recently completed piling for a new substation as part of the Triton Knoll Offshore windfarm project in Bicker Fen, Boston.

The new substation, which is connected to the windfarm via 40 miles of underground cable to the Lincolnshire coast, will convert the generated electricity from the windfarm for the National Grid.

Once completed, the windfarm will be capable of providing clean and sustainable energy to over 800,000 UK homes.

Aarsleff Ground Engineering previously installed over 1500No.200mm and 250mm square precast concrete piles in April for the foundations of the substation buildings and equipment.

Subsequently, Siemens awarded Aarsleff the piling works for a gas main bridge that crossed the 3.8km access road.

The project saw Aarsleff install 8no. 600mm diameter CFA piles of 15m lengths, which were located either side of the gas main.

CFA piles were specified due to minimal vibrations it creates as the piles are being
installed. Siemens then laid a concrete slab to create a bridge over the gas main and prevent any future damage from service vehicles and machinery driving down the access road.

Download
Case Study
A Soilmec SF50 piling rig being used to install CFA piles at the Triton Knoll Offshore Windfarm project.
A Soilmec SF50 piling rig being used to install CFA piles at the Triton Knoll Offshore Windfarm project.

It has been a pleasure to work with Siemens again at the Triton Knoll Substation. This project was also the debut of our new Soilmec SF50 piling rig which allows us to install CFA piles up to 25m lengths.

Kevin Hague

Aarsleff’s Managing Director