Newark Welcome Break

EFFICIENT DESIGN, DELIVERING OPERATIONAL EXCELLENCE FOR A SHEET PILING JOB CLOSE TO HOME

A sheet piling solution to bridge an existing sewer. The solution appears neat from the bank side.

Project Description

SCOPE OF WORKS 150 l.m of sheet pile wall & 2 x localised buttress walls and wailing beam systems

CLIENT Welcome Break

CONTRACT Design and Build

CONSTRUCTION PERIOD January 2023

Working for Welcome Break alongside Breheny Civil
Engineering, Aarsleff were contracted to install 150 lin.m
of retaining wall which was designed in house as a sheet
pile retaining wall. We also designed localised bespoke
buttress walls and waling beam system within the main
conventional sheet pile wall in order to bridge an existing
sewer. The solution appears neat from the bank side and
ensures there is no disruption to the existing civil
infrastructure of the road.

Download
Case Study
A sheet piling solution to bridge an existing sewer. The solution appears neat from the bank side.
Close-up of a sheet pile retaining wall along a bank. Bare trees are visible in the background.