Birtley Phase 3

ONGOING INDUSTRY COLLABORATION PROVIDES AN INNOVATIVE AND ROUNDED KING POST WALL SOLUTION

A construction worker in orange Aarsleff PPE guides a trench sheet being lowered by a crane.

Project Description

SCOPE OF WORKS: 133.5m king post wall, Retaining up to 3.7m

CLIENT: Vistry Partnership

CONTRACT: Design and build

CONSTRUCTION PERIOD: March – April 2023

Aarsleff Ground Engineering were contracted by Vistry Partnerships to install a 133.5m king post wall at the top of their Birtley development in order to allow excavation for gardens and house foundations to take place. The wall is retaining up to 3.7m and will be timber cladded once complete, forming a desirable ‘garden fence’ effect to the rear of the plots.

Due to early engagement from the client, Aarsleff’s design engineers were able to value-engineer the scheme, increasing the spacing of the king posts to reduce both resources and time. As the posts needed to be pre-bored, a reduction in posts overall not only had an impact on cost and the overall emissions of the project, but also reduced the time needed at both the drilling and post installation phases.

MGF’s involvement came from their long-standing working relationship with Aarsleff, they were asked to collaborate with the Aarsleff team on a solution which looked to provide a temporary panel design that would allow for the king post solution to be installed.

This wider spacing and the use of narrow UC203 sections meant that the typical precast concrete infills used for king post walls would be too thick to fit. During the design process, both teams worked collaboratively to design a more cost effective and sustainable solution than the standard concrete infill panels. Looking at a range of options that were available, the teams opted to use MGF KKD 600/8mm trench sheets in a horizontal application, with the sheets overlapped and welded to the king post sections. Where bending moments within the thin panels were too high for a single sheet, the risk was easily mitigated by doubling up the sheets. This allowed for more flexibility on the scheme as well, as the sheets could be cut on site if needed, and are quicker to source than precast panels, allowing us commence work on site earlier.

Download
Case Study
A construction worker in orange Aarsleff PPE guides a trench sheet being lowered by a crane.

“Birtley has been a rewarding project to be involved with and presented specific challenges. Temporary works had to be managed closely to ensure the safety of Aarsleff welders while fixing panel support brackets to the post below formation level. Due to the large retained height and top down construction method trench boxes were used in a unique way as temporary support panels. These were lifted behind the posts, retaining the ground in the temporary condition to enable the installation of infill panels at each bay.”

Alex Boyle

Graduate Engineer

A leading UK ground engineering specialist, focusing on multi-discipline excellence and value engineering. We design and deliver some of the UK’s largest ground engineering projects.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our vision is to bring confidence to those constructing the landscape of tomorrow .

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

1947. Central Jutland, Denmark. Per Aarsleff borrowed 10,000 Danish Kroner from his father’s life insurance, bought an excavator, and founded Northern Europe’s leading contracting company.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our biggest asset, our team is composed of the leading experts in ground engineering. Working with collaboration and cohesion at the core of our business, we can guarantee a quick and founded answer to all your questions.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

We recruit and reward our people based on our ‘Step into the Blue’ company culture, where we embrace the core values of Life and Health, Trust, and Responsibility.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

We do everything to ensure our team and yours work safely on our sites. With our core value of Life & Health, we see safety as a cultural pillar.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our ISO accreditations are an assurance to you that we take governance seriously. Read our policies to discover more.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

The projects that keep society running. Bridges, buildings, transit and rail facilities, embankment support, marine and offshore facilities, mines, airports, and water projects.

Close-up view of steel reinforcement cages at a construction site. A yellow KLEMM drilling rig is in the background.

Keeping things turning. Sewage Treatment Works, Waste Water Treatment Works, Wind Farms and Wind Turbines, Biomass Plants, and Power stations.

Aarsleff's Junttan PM 20HLC piling rig in operation with two workers present. Another piling rig can be seen in the background.

Meeting society’s needs. Nursing and care homes, MOD buildings, Schools and Universities, and small or large-sized residential developments.

Three piling rigs positioned on a muddy site under a blue sky. Construction workers are seen near the rigs.

Staying on the move. Remediation, bridges, and foundation work are integral to keeping the industry running smoothly.

Aarsleff worker kneeing down on one knee with a yellow piling rig and concrete piles in the background. The worker is wearing high-visibility clothing and a white hard hat.

The landscape of the marketplace. Mega-retail sheds, distribution warehouses, University accommodation, and major supermarket and household name units.

Commercial piling projects

Keeping things afloat. Ports and harbours, coastal defences, river embankments and inland waterways.

An aerial view of the Port of Hanstholm.