Guernsey is the second largest of the Channel Islands with an area of 24 square miles and a population of approximately 63,000 people. The island is located 75 miles south of Weymouth in England and 30 miles west of France’s Normandy Coast.

Aarsleff Ground Engineering were awarded the piling works by one of Guernsey’s longest-established building contractors, Rihoy & Son, for the construction of a new 4-storey office block and 4-storey steel frame car park. The site, which is based off Elizabeth Avenue in Admiral Park, will also feature Guernsey’s first Premier Inn hotel, along with a new restaurant and private office spaces.

Aarsleff supplied, handled and installed 331No. 178Ø thick walled steel tube piles to average of 8m lengths. The steel tubes, which are recycled from offshore oil and gas platforms, along with Aarsleff’s Junttan PM16 were shipped out from Portsmouth in mid-November, arriving in Guernsey on time to commence the piling works.

Aarsleff’s Senior Contracts Engineer Simon Cottington who oversaw the piling works said,

“It has been an interesting project, especially as it was the first time Aarsleff has worked in Guernsey. A lot of preparation was done beforehand, including a full service of our Junttan piling rig to reduce the risk of having any issues when on site. We also made sure within our team there we had a plant fitter and service parts available to keep our piling rig maintained if the machine broke down.”

Aarsleff were able to complete the works within the set programme and successfully return its equipment and team back to UK mainland before Christmas.

Download Case Study

A leading UK ground engineering specialist, focusing on multi-discipline excellence and value engineering. We design and deliver some of the UK’s largest ground engineering projects.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our vision is to bring confidence to those constructing the landscape of tomorrow .

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

1947. Central Jutland, Denmark. Per Aarsleff borrowed 10,000 Danish Kroner from his father’s life insurance, bought an excavator, and founded Northern Europe’s leading contracting company.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our biggest asset, our team is composed of the leading experts in ground engineering. Working with collaboration and cohesion at the core of our business, we can guarantee a quick and founded answer to all your questions.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

We recruit and reward our people based on our ‘Step into the Blue’ company culture, where we embrace the core values of Life and Health, Trust, and Responsibility.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

We do everything to ensure our team and yours work safely on our sites. With our core value of Life & Health, we see safety as a cultural pillar.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

Our ISO accreditations are an assurance to you that we take governance seriously. Read our policies to discover more.

An Aarsleff construction worker wearing a high-visibility jacket and hard hat on a site.

The projects that keep society running. Bridges, buildings, transit and rail facilities, embankment support, marine and offshore facilities, mines, airports, and water projects.

Close-up view of steel reinforcement cages at a construction site. A yellow KLEMM drilling rig is in the background.

Keeping things turning. Sewage Treatment Works, Waste Water Treatment Works, Wind Farms and Wind Turbines, Biomass Plants, and Power stations.

An Aarsleff Junttan PM 20HLC piling rig in operation with two workers present. Another piling rig can be seen in the background.

Meeting society’s needs. Nursing and care homes, MOD buildings, Schools and Universities, and small or large-sized residential developments.

Three piling rigs positioned on a muddy site under a blue sky. Construction workers are seen near the rigs.

Staying on the move. Remediation, bridges, and foundation work are integral to keeping the industry running smoothly.

Aarsleff worker kneeing down on one knee with a yellow piling rig and concrete piles in the background. The worker is wearing high-visibility clothing and a white hard hat.

The landscape of the marketplace. Mega-retail sheds, distribution warehouses, University accommodation, and major supermarket and household name units.

Commercial piling projects

Keeping things afloat. Ports and harbours, coastal defences, river embankments and inland waterways.

An aerial view of the Port of Hanstholm.