Ransom Moor

As a result of previous experience both in the UK and Europe Aarsleff, working to a design by Structural Engineers HCE Ing. mbH, were employed as the specialist piling contractor for the installation of 96no, 350mm square reinforced, precast concrete piles were driven to average lengths of 13m to form a stable foundation for the construction of 2no. REPower MM82 turbines.

RG Carter Civil Engineering Ltd were appointed by Fenpower Ltd to act as Balance of Plant Contractor to construct phase II of this wind farm at Ranson Moor, Cambridgeshire. Acting as Principle Contractor and supervising all works including the electrical installation up to the non-contestable DNO connection RGCCE are responsible for the successful completion of the Project.