Large scale piling for three new Office / Warehouse units in the East of England.
Project Description
SCOPE OF WORKS 5090nr. precast concrete piles/72,278m of precast piles installed EQUPMENT x4 Junttan PM20/22 Rigs
CONTRACTOR Glencar Construction
CONSTRUCTION PERIOD January – May 2022
Arrival on site was met with a slower start than anticipated,with a lack of information meaning the delivery team were not able to progress as quickly as initially expected.
The Project Delivery Team maintained high standards of communication both with the client and between project management and site in order to progress forward.
Hard work put in throughout by the site team meant that despite delays, timelines created at the tender stage were met and even surpassed in some cases.
The site crews worked tirelessly to make up for lost hours surpassing tender targets when possible. The efforts of Paul Gulliver and the site team were great and very much appreciated.
Jon Goodman
Contracts Engineer