To achieve the full performance of the sheet pile structure, sheet piles must be driven to the depth specified by the wall designer. This can be achieved through a number of methods – vibratory hammers, impact hammers, or a silent press if noise and vibration need to be eliminated. Corner and connector pieces are available for any sheet pile purchased, allowing the wall to follow the line laid out in the design.
Most scenarios will involve some preparatory work before you begin the construction of your sheet pile structure. Indeed, many sites will require excavation. To have more mobility in building, for burying anchors or ultimately changing the landscape, preparatory work will need to be done first.
Once the preparatory work is completed, the installation of steel sheet piles can be achieved by the following steps:
Let’s look at a case study. Chesterfield Associates Inc. commenced a project in November 2017 to replace the steel sheet piling on a pier at the Port Jefferson Ferry Terminal in New York state. The pier at Port Jefferson Ferry Terminal is about 300 feet long and 80 feet wide. The original structure, made of wood timbers, is about a hundred years old. It has been reframed at least a couple of times, most recently in the late 1980s.
A steel bulkhead ties into the landward end of the pier. Pile lengths required around the pier range from about 50 feet to 90 feet at the pier’s deepest point. The sheet piles installed in the 1980s had deteriorated in many places.
The new piles, at 0.625-inches thick, should have a longer service life of 50 to 60 years. This was the first job ever that Chesterfield Associates worked on that required two high mats. Moving the mats alone required six tractor-trailer loads. The longest sheet piles required for the depths of the project weighed eight tons a pair. Specialised stretch trailers transported two pairs at a time to the site.
Chesterfield Associates team extracted the old sheet piling from around the pier. About 40 metres of old piling was extracted and replaced at a time; the template used to hold the structure in line during this process is 40 feet long. Generally, the cycle of excavation, old pile extraction and new pile installation for the 40 feet would take two to three days, depending on bottom conditions; obstructions could add significantly to that time.
Requiring more power to install the new piling, the company rented a Model 50B vibratory hammer to drive up to 90 feet in the soil conditions at the pier. Sometimes when the old piling was being extracted, some of the previous structures moved into the path of the new piling. Divers were required to enter the water to deal with the obstructions.