Kier are pleased to recognise the positive contribution to collaborative working with our Safety, Health & Environment Management System requirements including our Just and Fair Culture Standard by your Site Supervisor Paul Newman on the above Project and as a result a green card has been issued as part of their recognition.

We thank you sincerely for raising and promoting SHE awareness within your own company, it enables our projects to become more efficient when working collaboratively and without incidents.

Whilst the green card is issued to your Site Supervisor Paul Newman, it is also recognised the quality and safety culture displayed by the remainder of your team under Paul’s leadership. This will also be recognised by our Procurement Team in the scoring of our Supply Chain.

 

Kier

Dave Lines
Senior Site Manager

Hythe Hospital

Fantastic team – really drove the programme and very sensible cost wise on quite a complicated ground solution.

ISG

Aidan Prior
Senior Surveyor

Littlebrook

I would like to take the opportunity to praise / thank Aarsleff for the work completed. There were a few issues on site which they overcame with no problems. Everything that was planned and had to be changed daily was met with the timescales explained. The management of the works was fantastic and we were kept up to date with all changes that were required.

The operatives on site were also fantastic, they worked as expected and with no issues / complaints. nmcn have a number procedures in place that need to take place daily and the Aarsleff supervisor ensured these were completed on time. They were accommodating to the local residents when asked anything regarding their work and they also worked within the times required for the site area.

I would have no issues in recommending Aarsleff for any future work for nmcn or any other contractor who is considering using Aarsleff. Great work, great job, Thanks.

nmcn PLC

Chris Gillespie
Project Manager

Extra Care Village, Boughton, Ollerton

They have completed a tremendous job and the customer service was absolutely cracking. Aarsleff excelled my expectations on this project, and happy with the service without a shadow of a doubt. Well done James for your delivery of our sheet piling, anchors and bespoke capping!

MCS Group

Phil Hawley
Project Manager

Griffiths Way, St. Albans

Excellent, professional service and we would highly recommend using Aarsleff.

Geol Consultants Ltd

Terry McMenam
Director

Grange Lane, Whickham

Outstanding site team, well organised, well managed, flexible and proactive, from manager to operators a credit to Aarsleff.

ISG

Gary Lambton
Construction Manager

Bowburn, Durham

All members of the piling team were faultless, a very difficult little job but with the assistance and full cooperation of your staff the piles went in without a hitch.

E.N. Suiter & Sons Ltd

Quinton Mitchell
Contracts Manager

Highgate School, Kings Lynn

Just a quick email to state our satisfaction with the works carried out last week and the manner in which the project was managed both on and off site. The professionalism shown from yourselves before and during the works is much appreciated. A special mention must go to your team who worked in a safe collaborative manner working closely with our ground works contractor. Thanks again and we look forward to working with you in the future.

Morgan Sindall Construction

Mark Stephens
Senior Project Manager

HMS Cambria

Your guys were great to work with. Always very helpful, never had to pull them up on health & safety matters and tidied up before they left at the end of the week. Would be glad to work with them again.

Devon Contractors

John Crowhurst
Site Manager

WestOne Phase 2

Aarsleff performed to the highest standards for safety and quality. I will be using Aarsleff again in the future.

Monostore

Nick Stringer
Head of UK

Eye Airfield Crown Chicken

I would just like to say and reiterate that your Site Team with James and Paul and all those involved in the Project have done a brilliant and professional job. Many thanks!

Jackson Civils

Andy Wargent
Project Manager

Clacton-on-Sea

Great service from start to finish, credit to Sam Riley, his expertise was critical in driving an alternative piling process required due to a variant in our site conditions that was initially not taken into consideration. From early correspondence it was evident that a high level of service was guaranteed. Their attendance onsite to discuss a design issue led to their specialist knowledge being fully embraced by all involved in this project and proved to be a key driver in amendment of the piling design to reflect the issues we encountered onsite. They were a pleasure to work with from start to finish and hope there are many more opportunities ahead to once again reignite our working relationship.

G Oakley & Sons

Alex Hart
Contracts Manager

Premier Inn, Woking

We employed Aarsleff Ground Engineering to undertake the piling and retaining wall package on Rochdale Riverside. We have been impressed by the approach Aarsleff have taken to design, supply and install this package. They are very proactive when it comes to proposing solutions to problems that occur in design and on site. I would recommend Aarsleff to others as they have proven their capability in delivering a high value piling package that has had numerous issues in both design and whilst on site. Aarsleff always looked to resolve any design issues directly with our design team and proposed numerous solutions that worked well on site. This pro-active approach ensured we were able to mitigate any delays to the project. Commercial issues have been dealt with in a timely manner and have been easy to resolve. I look forward to working with Aarsleff again in the near future.

Willmott Dixon

Michael Blackburn
Project QS

Rochdale Riverside

Thanks for a really quick response to our initial enquiry & for reacting to the changing timescales on this project. Euan Allison was a pleasure to deal with and the lads carrying out the works on site did a really good job & finished ahead of programme.

Peter Duffy Ltd

Andrew Daggers
Project Manager

Tophill Low Waste Treatment Works

Delighted with Stuart and Cory, there work ethic and such like on site has been second to none. You have two great men there, who have ticked all the right boxes here on site. I personally would have no hesitation in recommending them to anyone.

BHC ltd

James Russell
Site Manager

Deltagen Highbridge

I have found your operatives to be very helpful, on time and the job was finished on schedule.

Persimmon Homes

Mick Mcevoy
Senior Site Manager

Repton Park, Kent

Good communication. Site personnel were professional and very informative. A pleasure to work with. Steve Leather and Lee Severn were most accommodating and did an excellent job so please pass on our regards. Look forward to receiving quotations for future works.

Applegate Homes Ltd

Ryan Chappell
Construction Manager

Frampton Fen

A great team, headed up by Engineer Parth, and supervised by Paul on site. Very well organised, committed to safe and efficient working. It was a pleasure working with these guys.

Buckingham Group

Garry Mountain
Site Manager

York Community Stadium

I just wanted to drop you a line to say how pleased I have been with the team on site. Its gone very smoothly and they have been both helpful and pro-active. We will certainly be looking to use this system on our next sites.

AM Architectural Design Ltd

Andy Miles

Broom River House

The site team were as good as I have experienced before, no problem and very adaptable and helpful. Jon Harris also was very good and helpful in every way. Both management and site team are a credit to yourselves.

J Tomlinson

Steve Whiting
Senior Site Manager

Perkins, Oldbury

I thought Aarsleff worked very well and efficiently. I wouldn’t hesitate to work with them again in the future.

Kitto Group PLC

Chris Roberts
Contracts Manager

Weston Supermare Nursery

Thanks for the efforts on this project, it hasn’t gone unnoticed by the site team and this has been passed up the chain.

BAM Construction Ltd

Dean Gillies
Senior Project Surveyor - North East

Project Southwest Secondary School, Mercia, Sheffield

From the top, right down to the guys on site, Aarsleff are very pro-active, experienced, transparent and extremely well-organised.

NATM Magazine

James Durose-Rayner
Editor in Chief

The lads on site were extremely professional. They were good workers and have got on with everybody on site.

Taylor Pearson Construction

Simon Harrison
Supervisor

Project Old Leake, Boston, Lincolnshire

The most helpful company that we have dealt with in this field. We felt valued as a company. Aarsleff looked at our projects with a commercial view to getting us the best value for money. You offered a flexible and customer friendly service.

Barnack Estates UK Ltd

Mark Blackhurst

On-site experience was professional and worked in a good manner.

Persimmon Homes

Karl Shepherd

The Aarsleff team were faultless on all three visits to the site. The last project was at very short notice and they were with us within a week which meant that I could keep to my build schedule having got over the problems. Their crew was always neat and tidy and really got on with the job effectively and efficiently.

Persimmon Homes

Phil Jones
Site manager

Project Roebuck Park

Always very helpful & professional, generally very nice people to work with.

Firbeck Construction Ltd

Stephen Parker

Very helpful estimating department.

Tercon

James Boyles
Quantity Surveyor

Of course being a brownfield site there were the inevitable problems caused by obstructions. But Aarsleff demonstrated a refreshing approach to these and simply relocated to an area where they could work whilst the matter was being dealt with. The result was that by working together the works were completed on programme and within budget. As a result of their performance on the JunXion, and also their specialist knowledge and experience of working in the Lincoln area, we contacted Aarsleff in the first instance with a mind to continue the good working relationship that had been built up previously.

North Midland Building Ltd

Mike Caitlin
Managing Director

Aarsleff’s team on site were professional throughout the entire duration of the project and their level of technical expertise became apparent with the works being completed well ahead of schedule and without any issues.

Midas Construction Limited

Guy Salazar-Lewis
Site Manager

Aarsleff carried out all the piling work in an efficient manner and in accordance with our build programme deadlines.

Lawley Village Development Group

Stuart Meredith
Project Engineer

With multiple developers, Aarsleff has worked with consortium members to overcome the practical difficulties of piling where properties are developing at different rates in close proximity to each other.

Persimmon Homes, part of Lawley Village Development Group

Phil Tiley
Technical Manager

In our experience on this project, Aarsleff has performed as a professional and competent company.

Barratt West Midlands, part of Lawley Village Development Group

Lee Perry
Technical Director

I was very impressed with the site crew, we had prepared the site which has a lot of made up ground, in line with the platform layout and specification. However it was found that the operating space was limited but the Aarsleff crew worked around this problem and did not lose any time.

MWH

Stefan Erbes
Site manager

Project Dalmuir Waste Water Treatment Works

The two abutments of the 64-metre span temporary bridge over the River Ure at Ripon City Quarry are each founded on 300mm square precast concrete driven piles, supplied and driven by Aarsleff. Ground conditions and persistent flood risk presented significant challenges. Piles were generally 12m long on the Southside and 25m long on the Northside. Aarsleff proved flexible in their approach and were able to install the piles when river levels were low but continually changing. The last launch of the bridge was successfully completed on 20 January 2014, in readiness, for the 50 Tonne Dump trucks it will carry.

Aggregate Industries Ltd

Martin Owen
Group Engineer

Project Ripon City Quarry

We engaged Jon Harris of Aarsleff three months prior to works commencing, as with previous contracts, we have found his depth of knowledge in tidal conditions a great advantage in planning piling and new structure projects. The team placed on these works were a credit to Aarsleff, as their priority was Health, Safety and Quality throughout.

VolkerFitzpatrick

John Gallagher
Site Manager

Project Southend on Sea, Beach Access

Aarsleff has been absolutely fantastic, brilliant, I can’t fault them. There was only one week where the low tides would allow us to work on the beach and install the piles. Aarsleff didn’t need the working platform as the beach was able to support their rig and they completed the piling in just three tides, instead of the seven predicted. The line of the installed piles couldn’t be better and will help us when we come to reassembling all the additional timber bracing. Aarsleff has been extremely helpful right from the start of us contacting them from our search on Google. We saw on their website that Aarsleff had been involved with other marine piling projects. Aarsleff was also recommended to us, as they had successfully installed about 6000 greenheart piles for new groynes on the beach just along the coast at Eastbourne in the 1990s. There are some more piles to be replaced here on the southwest corner of the landing stage and if Aarsleff’s price is okay we would anticipate they could also install those.

Paine Manwaring Green Ltd (PMG)

Alistair Ktori
Works Director

Project Worthing Pier

We have worked with Aarsleff on many developments and as expected this project ran true to schedule. We had cleared the site a couple of years ago and were able to provide a good stable and level base for the rig to operate on. Fortunately we have plenty of easy access for the pile delivery and holding. The drive went well and the crew were meticulous in positioning the rig. We expect to be working with Aarsleff again soon.

JR Smart

Gareth Smart
Development Director

Project Capital Quarter Cardiff

I couldn’t fault the Aarsleff team who worked very hard on our project. They were well disciplined and courteous and managed the safety and deliveries procedures perfectly. They were a credit to Aarsleff and to the construction industry and they are just the type of team we would always wish to work with.

Sewell Construction Ltd

Martin Standley
Project Manager

Project Commercial Extension Hull

It’s essential to have an experience, dependable piling contractor geared up to supply and install piles and to work as quickly as they have. Aarsleff’s ability to feed the process in-house, make piles and install them is a big advantage. We had an initial stock of piles on site when we first started, but once we were up and running we moved onto a just-in-time basis, which worked really well. I was pleased with the piling operation, which was always ahead of the programme.

Shepherd Construction (Now part of Wates Group)

Phil Bradley
Project Manager

Project IKEA Peterborough

The piling job was spot on. The design was excellent and the production was first class. I was very impressed with the Aarsleff operation and will be happy to use them again when we need piling for a project in the future.

Wates Construction

Steve Hart
Project Manager

Project Selby Leisure Complex

Aarsleff’s approach to their sub-contract works was completely refreshing. The Tower Wharf project required fast-track procurement to meet a strict planning restriction on piling operations. Both Aarsleff’s Commercial and Construction teams ensured the commencement date on site was achieved and their works delivered within the timeframe. Aarsleff has a truly professional approach in undertaking their works.

Eric Wright Construction

Simon Milligan
Project Manager

Project Tower Wharf, Birkenhead

It was encouraging to see how Aarsleff approached this project from the offset. Their team’s proactive mind-set of realising the important of pre-start planning and upfront technical advice was second to none. This positive approach was carried through to the site team’s attitude in dealing with the daily challenges of on-site activities throughout the project until completion. Some 10,000 piles overall, driven within a very tight programme, all without any fuss or complications. Aarsleff’s approach to Health and Safety is impeccable. Using fully serviced, modern machinery and up-to-date working practices, ensured this was one less challenge to overcome. We look forward to working with the Aarsleff team again.

Bowmer & Kirkland

Ben Howard
Project Manager

Project NEXT Doncaster

We have a good working relationship with Aarsleff and worked closely together to come up with some viable options and agreed on a format to move forward using two different rigs with bigger hammers and different driving capabilities. I’m very impressed with Aarsleff’s professional manner in dealing with the unexpected and we will now work together on our next wind farm project in Bristol.

Ecotricity

Simon Vince
Project Manager

Project Bambers Windfarm

Aarsleff Ground Engineering were employed as a subcontractor on the Wakefield Waste Project at South Kirkby to supply and install 906 precast driven piles to two areas on site, within a seven-week period. They completed the works seven days ahead of their scheduled date, in spite of an initial delay due to design testing requirements. Then, due to a design change to one of the areas of the project, Kier instructed Aarsleff to manufacture and install an additional 185 piles, which they did in just over three weeks from receiving the design information – almost two weeks quicker than our original planned duration for the works. We found Aarsleff’s’ management and site operatives easy to work with and very efficient with regards to design, installation and testing. Overall working with Aarsleff was a stress-free and pleasant experience and I would definitely consider them again for future works.

Kier Infrastructure

Chris Scarr
Sub Agent

Project South Kirkby Waste Management Facility

Get a quote

For more information about Aarsleff Ground Engineering or to send in your enquiry,
call 01636 611140 and speak to an expert member of our team today.

A leading UK ground engineering specialist, focusing on multi-discipline excellence and value engineering. We design and deliver some of the UK’s largest ground engineering projects.

Our vision is to bring confidence to those constructing the landscape of tomorrow .

1947. Central Jutland, Denmark. Per Aarsleff borrowed 10,000 Danish Kroner from his father’s life insurance, bought an excavator, and founded Northern Europe’s leading contracting company.

Our biggest asset, our team is composed of the leading experts in ground engineering. Working with collaboration and cohesion at the core of our business, we can guarantee a quick and founded answer to all your questions.

We recruit and reward our people based on our ‘Step into the Blue’ company culture, where we embrace the core values of Life and Health, Trust, and Responsibility.

We do everything to ensure our team and yours work safely on our sites. With our core value of Life & Health, we see safety as a cultural pillar.

Our ISO accreditations are an assurance to you that we take governance seriously. Read our policies to discover more.

The projects that keep society running. Bridges, buildings, transit and rail facilities, embankment support, marine and offshore facilities, mines, airports, and water projects.

Keeping things turning. Sewage Treatment Works, Waste Water Treatment Works, Wind Farms and Wind Turbines, Biomass Plants, and Power stations.

Meeting society’s needs. Nursing and care homes, MOD buildings, Schools and Universities, and small or large-sized residential developments.

Staying on the move. Remediation, bridges, and foundation work are integral to keeping the industry running smoothly.

The landscape of the marketplace. Mega-retail sheds, distribution warehouses, University accommodation, and major supermarket and household name units.

Keeping things afloat. Ports and harbours, coastal defences, river embankments and inland waterways.

Technically trained estimators and a dedicated, in-house design team means we consider value-engineering at every stage of your project.

More than just a model, Visual Design & Construction is a tool to encourage collaboration and improve quality across all facets of a scheme.

From large commercial sheds to small residential plots, piling could be the foundation solution you need to support your project.

Issues around collapse, slipping or erosion? Our experts in retaining solutions have a broad portfolio of techniques designed to fix even the most nuanced of sites.

Tricky ground conditions or requirements? Aarsleff’s ground engineering team work on stabilisation through a varied range of techniques, bespoke to the properties of your site ground.

Our plant workshop offers a range of services designed to ensure your plant works for you. Whether it’s manufacturing and fabrication of equipment for long-term needs or hire so you can complete something specific.