Aarsleff have worked on a number of marine piling projects, Worthing Pier being one of them. Check out our case study on our website for more information about the project by clicking here.

“There was only one week where the low tides would allow us to work on the beach and install the piles. Aarsleff didn’t need the working platform as the beach was able to support their rig and they completed the piling in just three tides, instead of the seven predicted. The line of the installed piles couldn’t be better”