On Site at Preston wwtw (2)

Driven Precast Concrete Piling for Preston Waste Water Treatment Works: Aarsleff has completed the design, supply, delivery and installation for piling works at Preston’s new Waste Water Treatment Works (WWTW). After a small trial piling exercise in June, Aarsleff began the main works installing over a thousand 250mm square precast concrete piles for the storm tank. Aarsleff then re-mobilised 1 rig to finish off in November with final completion in January.

Over the duration of 31 piling weeks split over 2 phases, Aarsleff worked to a tricky sequence, however, with a bit of co-ordination and co-operation, managed to successful install the piles.