Aarsleff has announced that it has completed a 17 week piling contract for fashion retailer Next in Doncaster.

Over 9,500 precast concrete piles were installed for the new 58,000m2 distribution centre at West Moor Park which is being constructed by Bowmer and Kirkland.

The tight schedule meant that designs were only completed ahead of the piling work, so Aarsleff worked closely with its pile manufacturing division Centrum Pile to minimise the number of different pile sizes used on the site and maximise availability of piles for the work.

Aarsleff also drafted in low bearing pressure Junttan piling rigs to complete the work and minimise the thickness of the piling platform needed.