Clay Cross, Chesterfield King Post Installation

Aarsleff Ground Engineering have completed on site in Clay Cross, Chesterfield installing retaining walls for a new housing development.

The Egstow Park development will have over 160 houses on the site, ranging from two-bedroomed homes all the way up to four-bedroom. The development is also located with good transport links into Chesterfield, along with great outdoor space and only a short distance from the Peak District.

Aarsleff were awarded the contract by St. Modwen Homes for the construction of the retaining walls on the site. Aarsleff proposed a King Post Wall solution as an alternative to the sheet piled wall St. Modwen Homes were originally looking for as it provided a faster construction and more aesthetic finish.

In total, Aarsleff installed 106 Lin/m of King Post Wall around part of the site with maximum retained heights of up to 2.6m. The construction of the wall involved driving H-section posts spaced 1.5m apart using a crane suspended vibratory hammer. Once installed, the pre-stressed concrete panels were placed between the posts to create the wall. The wall was then back filled to retain the bank and allow maximum usage of the site.

Read more…

Download Case Study

,