Channel Tunnel Rail Link / High Speed 1

DRIVING OF PRECAST PILES FOR HIGH SPEED 1 RAIL PROJECT

Project Description

SCOPE OF WORKS 3,000 No. 600 x 600mm, L=9.5 – 18m precast reinforced concrete piles
CLIENT Morgan-Vinci JV
EQUIPMENT Hitachi KH180.3 GLSK, Aarsleff’s Low Headroom Rig
CONSTRUCTION PERIOD Jul 2002 – Jan 2004

Following the UK Government’s approval for two sections of 69-mile high-speed Channel Tunnel Rail Link (CTRL), now referred to as HS1, the project, specifically CTRL Contract 310 West Thames Ribble Lane to Thurrock, was put out to tender and awarded to main contractors Morgan-Vinci, as a joint venture.

This enormous and complex project required vast amounts of foundation works, including piles to support sections of the 7-km,10m-wide reinforced concrete track slab that carries the high speed line over the soft West Thames marshes at Havering an Thurrock, Essex, ground that can comprise up to 10m of alluvium over flood plain deposits, tertiary clays and sands or chalk.

Arrsleff’s tender was successful in winning the piling contract, valued at approximately £4.25M. The scope of the project was to install 3,000 specially manufactured 600mm x 600m square section precast concrete piles, in lengths varying from 9.5m to 18m in rows of four and six at 5m centres, to support the reinforced concrete track slab.

With the estimated 18-month project commencing in July 2002, work on casting the 600mm square section continuously reinforced concrete piles began in June 2002.
The Piles were cast using Centrum Pile’s proven free-flowing, self-compacting concrete mix, which does not require any vibration, flowing into the moulds and around the rebar, which had a tried-and tested history having been used previously in the manufacture of the company’s smaller, standard square section reinforced precast concrete piles.

Additionally, the CTRL piles also incorporated full length chamfered corners and domed heads, typical of Centrum Pile’s standard design features, which eliminated the need for reinforced bands required for driving conventional flat-topped piles.

The perfectly symmetrical 600mm square section piles were cast in 14.2m long single length segments, which weighed 12.5 tonnes using purpose built moulds. A special rigid mechanical joint was also cast into the ends of some piles to achieve the necessary 18m maximum length required on site.

The sections of the steel moulds were individually formed and separated between each section and a combination of cams and hydraulic rams locked the sides of the moulds in the vertical during casting.

Download
Case Study

A leading UK ground engineering specialist, focusing on multi-discipline excellence and value engineering. We design and deliver some of the UK’s largest ground engineering projects.

Our vision is to bring confidence to those constructing the landscape of tomorrow .

1947. Central Jutland, Denmark. Per Aarsleff borrowed 10,000 Danish Kroner from his father’s life insurance, bought an excavator, and founded Northern Europe’s leading contracting company.

Our biggest asset, our team is composed of the leading experts in ground engineering. Working with collaboration and cohesion at the core of our business, we can guarantee a quick and founded answer to all your questions.

We recruit and reward our people based on our ‘Step into the Blue’ company culture, where we embrace the core values of Life and Health, Trust, and Responsibility.

We do everything to ensure our team and yours work safely on our sites. With our core value of Life & Health, we see safety as a cultural pillar.

Our ISO accreditations are an assurance to you that we take governance seriously. Read our policies to discover more.

The projects that keep society running. Bridges, buildings, transit and rail facilities, embankment support, marine and offshore facilities, mines, airports, and water projects.

Keeping things turning. Sewage Treatment Works, Waste Water Treatment Works, Wind Farms and Wind Turbines, Biomass Plants, and Power stations.

Meeting society’s needs. Nursing and care homes, MOD buildings, Schools and Universities, and small or large-sized residential developments.

Staying on the move. Remediation, bridges, and foundation work are integral to keeping the industry running smoothly.

The landscape of the marketplace. Mega-retail sheds, distribution warehouses, University accommodation, and major supermarket and household name units.

Keeping things afloat. Ports and harbours, coastal defences, river embankments and inland waterways.

Technically trained estimators and a dedicated, in-house design team means we consider value-engineering at every stage of your project.

More than just a model, Visual Design & Construction is a tool to encourage collaboration and improve quality across all facets of a scheme.

From large commercial sheds to small residential plots, piling could be the foundation solution you need to support your project.

Issues around collapse, slipping or erosion? Our experts in retaining solutions have a broad portfolio of techniques designed to fix even the most nuanced of sites.

Tricky ground conditions or requirements? Aarsleff’s ground engineering team work on stabilisation through a varied range of techniques, bespoke to the properties of your site ground.

Our plant workshop offers a range of services designed to ensure your plant works for you. Whether it’s manufacturing and fabrication of equipment for long-term needs or hire so you can complete something specific.